| DESCRIPTION |
START (5/21/04) |
REVISED START |
COMPLETION (5/21/04) |
REVISED COMPLETION |
| Authorized Start of Construction |
|
|
3/29/04 |
|
| Install Construction Protection Fencing |
5/04 |
|
5/04 |
|
| Design and Specifications |
|
|
|
|
| Initial Design |
|
|
1/02 |
|
| As built |
5/04 |
|
3/05 |
|
| Access Road |
|
|
|
|
| Powerhouse |
5/04 |
|
5/04 |
|
| Intake |
5/04 |
|
8/04 |
|
| Penstock Intake Structure |
|
|
|
|
| Surveying |
4/04 |
|
6/04 |
|
| Excavation |
5/04 |
|
5/04 |
|
| Forms & Concrete |
5/04 |
|
6/04 |
|
| Mechanical and Electrical Equipment
Installation
|
7/04 |
|
11/04 |
|
| Forebay Channels |
6/04 |
|
9/04 |
|
| Powerhouse |
|
|
|
|
| Surveying |
5/04 |
|
7/04 |
|
| Excavation |
4/04 |
|
6/04 |
|
| Concrete |
|
|
|
|
| Tailrace |
6/04 |
|
11/04 |
|
| Turbine Pad |
6/04 |
|
6/04 |
|
| Generator Pad |
6/04 |
|
6/04 |
|
| Switchgear Pad |
6/04 |
|
7/04 |
|
| Subfloor Footers |
6/04 |
|
7/04 |
|
| Subfloor |
6/04 |
|
8/04 |
|
| Steel Superstructure |
|
|
|
|
| Apply for Superstructure
Building Permit |
7/04 |
|
7/04 |
|
| Construction of Superstructure
per Building Permit |
9/04 |
|
11/04 |
|
| Mechanical Installation |
|
|
|
|
| Turbine and Generator Install |
10/04 |
|
12/04 |
|
| Electrical Installation |
|
|
|
|
| Swithgear and Control Install |
10/04 |
|
2/05 |
|
| Penstock |
|
|
|
|
| Upper Penstock |
8/04 |
|
11/04 |
|
| Lower Penstock |
8/04 |
|
11/04 |
|
| Diversion Changes |
|
|
2/03 |
|
| Transmission Line |
|
|
|
|
| Surveying |
5/04 |
|
5/04 |
|
| Securing Components |
5/04 |
|
8/04 |
|
| Installation |
8/04 |
|
10/04 |
|
| Interconnection by Idaho Power |
12/04 |
|
2/05 |
|
| Substation |
|
|
|
|
| Concrete pad |
6/04 |
|
7/04 |
|
| Transformer Installation |
9/04 |
|
9/04 |
|
| Switches and Controls Installation |
10/04 |
|
12/04 |
|
| Acceptance |
2/05 |
|
4/05 |
|