DESCRIPTION START (5/21/04) REVISED START COMPLETION (5/21/04) REVISED COMPLETION
Authorized Start of Construction     3/29/04  
Install Construction Protection Fencing 5/04   5/04  
Design and Specifications      
Initial Design     1/02  
As built 5/04   3/05  
Access Road    
Powerhouse 5/04   5/04  
Intake 5/04   8/04  
Penstock Intake Structure    
Surveying 4/04   6/04  
Excavation 5/04   5/04  
Forms & Concrete 5/04   6/04  
Mechanical and Electrical Equipment Installation 7/04   11/04  
Forebay Channels 6/04   9/04  
Powerhouse    
Surveying 5/04   7/04  
Excavation 4/04   6/04  
Concrete    
Tailrace 6/04   11/04  
Turbine Pad 6/04   6/04  
Generator Pad 6/04   6/04  
Switchgear Pad 6/04   7/04  
Subfloor Footers 6/04   7/04  
Subfloor 6/04   8/04  
Steel Superstructure    
Apply for Superstructure Building Permit 7/04   7/04  
Construction of Superstructure per Building Permit 9/04   11/04  
Mechanical Installation        
Turbine and Generator Install 10/04   12/04  
Electrical Installation        
Swithgear and Control Install 10/04   2/05  
Penstock    
Upper Penstock 8/04   11/04  
Lower Penstock 8/04   11/04  
Diversion Changes     2/03  
Transmission Line        
Surveying 5/04   5/04  
Securing Components 5/04   8/04  
Installation 8/04   10/04  
Interconnection by Idaho Power 12/04   2/05  
Substation        
Concrete pad 6/04   7/04  
Transformer Installation 9/04   9/04  
Switches and Controls Installation 10/04   12/04  
Acceptance 2/05   4/05